RECYCLE: REthinking low Carbon hYdrogen production by Chemical Looping rEforming
Funding body: Department of Energy Security and Net Zero
Funding budget: £5.1M
Project partners: The University of Manchester, Johnson Matthey, TotalEnergies, Kent plc, Helica Energy, ERM
The RECYCLE concept relies on a chemical looping process operated at high pressures in adiabatic packed bed reactors. It consists of three dynamically operated reactors. Each reactor is sequentially exposed to:
• Exothermic oxidation of the oxygen carrier using air to generate heat, which remains stored inside the bed
• Reduction of the oxygen carrier using any available low-grade off-gas which is converted into CO2 and H2O
• Endothermic reforming of a methane based gaseous fuel into syngas (CO and H2) and cooling the reactor to result overall thermally balanced. This intensified process represents a high level of novelty since it combines syngas generation, direct heat transfer and CO2 capture in a single unit.
The demonstration rig has been designed, built and is currently being installed in JCB. It consists of several modules:
• Reactors + Syngas coolers skid
• WGS + heat exchanger skid
• Boosters skid
• Desulphuriser skid
• Pump + Water tank skid
• PSA skid
• Control panel
• Analytical unit
• Air Package unit
Funding body: Department of Energy Security and Net Zero
Funding budget: £5.1M
Project partners: The University of Manchester, Johnson Matthey, TotalEnergies, Kent plc, Helica Energy, ERM
The RECYCLE concept relies on a chemical looping process operated at high pressures in adiabatic packed bed reactors. It consists of three dynamically operated reactors. Each reactor is sequentially exposed to:
• Exothermic oxidation of the oxygen carrier using air to generate heat, which remains stored inside the bed
• Reduction of the oxygen carrier using any available low-grade off-gas which is converted into CO2 and H2O
• Endothermic reforming of a methane based gaseous fuel into syngas (CO and H2) and cooling the reactor to result overall thermally balanced. This intensified process represents a high level of novelty since it combines syngas generation, direct heat transfer and CO2 capture in a single unit.
The demonstration rig has been designed, built and is currently being installed in JCB. It consists of several modules:
• Reactors + Syngas coolers skid
• WGS + heat exchanger skid
• Boosters skid
• Desulphuriser skid
• Pump + Water tank skid
• PSA skid
• Control panel
• Analytical unit
• Air Package unit
×