    This document presents the progress of WP2 Task 1.1, Task 1.2 and Task 1.3 as part of Deliverable 2. First, an initial statistical quantification of LV network constraints due to changes in voltages (Task 1.3) is presented. Thereafter the methodology to model real HV networks from DiNIS export files into OpenDSS is described (Task 1.1). Finally, an initial quantification of the allowable voltage reduction at primary substations (Task 1.3) is carried out adopting a time-series analysis (Task 1.2) and one real HV network.